|
J-Ditch
Pipeline Assoc.
McCall, Idaho
CES
designed and performed project engineering for the installation
of this two phase project. The project irrigates approximately 4,200
acres of pasture and seed potato ground near McCall, Idaho and was
funded through a variety of State and Federal programs. City of
McCall wastewater is delivered (a third phase installed by McCall)
to the J-Ditch Pipeline where it is mixed with fresh water for delivery
under gravity pressure to approximately 18 landowners. The J-Ditch
Pipeline Association (JDPAI) was formed as a non-profit private
corporation to install both the pipeline portion and the on-farm
portion of the project.
Pipeline
Project: CES designed this approximately 20 mile pipeline network
for the delivery of both fresh water and City of McCall wastewater
to the project area. The system includes duel 30-inch PVC mainlines,
irrigation diversion structure and flow measurement vault equipped
with trans-sonic flow meters for accurately mixing fresh and process
water. CES completed the design and developed drawings, specifications,
contracting and bid documents. On-site project engineering and construction
inspection was provided with additional inspection by the Valley
Soil and Water Conservation District.
On-Farm
Irrigation Project: CES also provided project engineering for
the on-farm irrigation system portion of the project. Approximately
20 center pivots, many wheel lines and solid set big guns have been
installed. CES worked extensively with the NRCS and local land-owners.
NRCS provided initial landowner plans, although all plans were modified
as requested by landowners prior to installation.
City
of Ontario
Ontario, Oregon
CES
has been employed by the City of Ontario (City) via a Master Service
Agreement since 1996. Significant project accomplishments include:
Bentonite
Lining of Wastewater Ponds: CES provided engineering design
for the rehabilitation of two lagoon cells totaling approximately
46 surface acres. A detailed alternative analysis was performed
evaluating the cost and performance of six alternative lining systems.
The selected design was a 15 percent bentonite lining on the bottoms
of the lagoons and covered PVC lining on the sides on the lagoons.
The primary consideration for the selection of a bentonite liner
was the expected presence of "bio-gas", although cost
was also a significant consideration. CES specified Teague Mineral
Product's, located in nearby Adrian, Oregon, as the approved source
of bentonite following detailed testing and evaluation. In addition
to lining the lagoon cells, several dikes were raised to provide
additional cost effective storage. CES provided preliminary design
criteria to the Oregon Department of Environmental Quality (DEQ)
prior to having the design approve by DEQ. The project was funded
under the Oregon State Revolving Fund and CES developed all project
engineering documentation required by this program. CES provided
the City with comprehensive designs, specifications, contract and
bid documents in addition to providing engineering oversight and
inspection throughout the project. This $1.1 million project was
completed on time and under the engineer's cost estimate.
Facilities
Plan Update: A comprehensive Facilities Plan was prepared for
the City addressing the treatment and disposal of the City's expected
increase in wastewater flows due to the Snake River Correctional
Institute's (SRCI) expansion. Key components of the this analysis
included the benefits versus cost of land application of wastewater
effluent, additional storage and increased discharge to the Snake
River. CES provided alternative analysis for two land application
areas which included site characterization and engineering economic
analysis. This Facilities Plan was approved by both the City Council
and DEQ. CES provided leadership for public and City Council input
throughout the planning process. A key component of the Facilities
Plan was an analysis of the economic impacts related to wastewater
treatment due to the SRCI expansion. This information formed the
basis for the City's negotiation with the Oregon Department of Corrections
to cost share for project installation.
Evaluation
of Wastewater Application on the City Golf Course: As a result
of significant public output, the City authorized CES to conduct
an evaluation of using the City's golf course for Wastewater Land
Application. This study reaffirmed the facilities Plan Update and
positioned the City for increased public investment at the golf
course and related facilities.
Outfall
Diffuser: At the direction of DEQ, the City authorized CES to
design an improved outfall diffuser for the discharge of wastewater
to the Snake River. CES utilized the DEQ recommended CORMIX model
and was able to show that the City's diffuser was currently in compliance
and expected to remain in compliance for the next 20 years with
DEQ standards. As a result, DEQ did not require the City to invest
in an improved outfall diffuser.
Recommended
Plan Project Design: CES completed the design of the Facilities
Plan Recommended Plan. Design assistance was provided by Earth Tech
who teamed with CES to deliver the design in a timely manner. CES
was the lead on the project which involved:
- Wastewater
Main Pumping Station: A supplemental pumping station was added
to the City's current pumping station to deliver water to the
proposed Land Application site. This pumping station includes
all electrical controls and systems required to meet the project
requirements.
- 4.5
Mile Wastewater Transmission Line:
A 4.5 mile wastewater transmission line was designed to transport
wastewater to a new storage reservoir and Land Application site.
Two segments of this project have already been installed with
CES providing project engineering services (design, specification,
bid documents, construction management and inspection). This first
section was the Malheur River crossing and the second section
involved crossing private landowner's property prior to the upcoming
irrigation season.
- 80
Million Gallon Storage Reservoir: CES has completed the design
of an 80 million gallon storage reservoir located 4.5 miles from
the City's current wastewater treatment plant. This reservoir
was lined with an HDPE liner and contains approximately 75,000
cubic yards of earthfill. Design and geotechnical evaluation was
performed by a team of CES engineers and geologists.
- 400
Acre Wastewater Land Application System and Pumping Station:
CES designed the 400 acre irrigation system and pumping station.
|