|
Tenaska,
Inc.
Shiro, Texas
CES
provided an evaluation for land application design. This included
a complete soils characterization to determine the potential issues
the land application site might present both to equipment and management.
CES also
developed a crop management plan for the Texas Natural Resource
Conservation Commission (TNRCC) as part of the permit requirements.
This site was also thoroughly investigated to establish the baseline
soil fertility. As this work was being completed, the preliminary
design and engineering costs estimates were developed for the pump
station, pipeline, electrical distribution, land application system
and controls. CES was retained to manage the establishment of the
Bermuda grass to meet the cropping requirements of the site. The
site became operational in 2000.
As
part of the project, CES:
- Adapted
site with poor physical soil properties to manage blow-down water.
- Developed
cropping plan to treat high salinity water from generator cooling
towers.
- Received
praise from the Texas regulator agency, the TNRCC, for high quality
site characterization study and management plans.
- Provided
fast track turn-key construction that maintained the generator
startup schedule; eight months, start to finish.
- Provides
operational services.
- Provides
on-going monitoring and reporting services.
Tenaska
Features
- Phase
I: Land application 5 pivots, Phase II: 7 pivots and solid set
- Pump
station
- Land
application to 193 acres
Portland
General Electric Company
Portland, Oregon
The
Portland General Electric Company (PGE) selected the Port of Morrow
industrial park, located near Boardman, Oregon, as the site for
the construction of the Coyote Springs co-generation power plant.
Between 1994 and 1996, CES assisted PGE and Port of Morrow in obtaining
permit modifications for the Port's 3,000 acre land application
system to accept the process water from the proposed facility (boiler
water and cooling tower water). This work included blended process
water characterization, predicted effects of application to land
and groundwater, a statement of knowledge describing existing and
proposed process water discharges, as well as a work plan for the
revised re-use system.
CES also
conducted an updated soil and hydrogeologic characterization as
it related to acceptance of the PGE process water. CES was able
to demonstrate to the Oregon Department of Environmental Quality
(DEQ) that the addition of the process water would not have detrimental
effects on the Portland application program. Permit modifications
were issued by the DEQ and the facility was constructed and began
operation in 1997.
Hermiston
Generating
Hermiston, Oregon
CES
was retained to complete design plans and water discharge permitting
for a process water land application system to reuse all cooling
tower blow-down water. The project involved the assessment and economic
analysis of potential land application sites, the design of a five-mile
process water pipeline, pump stations, integration with existing
irrigation system components, regulatory permitting and operational
management and monitoring plans. The project became operational
in 2001.
|